As we previously mentioned previously there is a serious chip shortage that will lead to supply issues and higher prices for single board computers and other electronics products. A few days ago, Hardkernel had o increase the price for ODROID boards using DDR4 memory with increases of $3 to $4 for ODROID-N2+, ODROID-C4, and ODROID-HC4 boards.

But besides price increase, some semiconductors will not be available at any price with extended periods as lead times of up to 52 weeks have been reported as shown in the table below, obtained from a trusted, anonymous source, which I have translated from Chinese.

Supplier Current lead time Increase in Q1
Memory
Micron 14-15 weeks 6-8 weeks
Alliance Memory 14-15 weeks 6-8 weeks
ADATA 14-15 weeks 6-8 weeks
Greenliant 10-24 weeks 2-12 weeks
Wang Hong Electronics 20-28 weeks 8-10 weeks
Transcend 14-15 weeks 6-8 weeks
MCU & Power Management ICs
NXP 26-52 weeks 8-12 weeks
Renesas 26-52 weeks 8-12 weeks
STMicroelectronics 26-52 weeks 8-12 weeks
Microchip 16-40 weeks 4-10 weeks
Qualcomm 26-52 weeks 8-12 weeks
Nuvoton 26-52 weeks 8-12 weeks
Analog ICs
Texas instruments 20-24 weeks 8-12 weeks
NXP / Freescale 20-24 weeks 8-12 weeks
Renesas 20-24 weeks 8-12 weeks
Toshiba 20-24 weeks 8-12 weeks
ON Semiconductor 16-52 weeks 4-10 weeks
Infineon 22-40 weeks 4-10 weeks
STMicroelectronics 16-30 weeks 2-4 weeks
MOSFET, Discrete devices
ON Semiconductor 22-50 weeks 8-12 weeks
Infineon 22-44 weeks 8-12 weeks
STMicroelectronics 22-40 weeks 4-12 weeks
Anshi semiconductor (Wingtech) 12-30 weeks 6-14 weeks
Rohm 20-40 weeks 8-20 weeks
DIODES 18-30 weeks 8-12 weeks
Littlefuse 16-30 weeks 4-8 weeks
CPU
Intel 12-16 weeks 8 weeks
Passive components
Vishay 24-52 weeks 8-12 weeks
Murata 20-26 weeks 6-10 weeks
Nichicon 16-24 weeks 6 weeks
Matsushita 16-30 weeks 4-12 weeks
Taiyo Yuden 18-20 weeks 2 weeks
TDK 22-44 weeks 6-12 weeks
Yageo 20-24 weeks 2-4 weeks
Wireless communication chips
Broadcom 24-52 weeks 8-12 weeks
MediaTek 20-30 weeks 8-10 weeks
Realtek 20-30 weeks 8-10 weeks
Microchip 24-26 weeks 6-8 weeks
Infineon/Cypress 26-30 weeks 16-18 weeks
u-blox 26-30 weeks 16-18 weeks
NXP 30-32 weeks 6 weeks

But besides price increase, some semiconductors will not be available at any price with extended periods as lead times of up to 52 weeks have been reported as shown in the table below, obtained from a trusted, anonymous source, which I have translated from Chinese.

originally published hwww.cnx-software.com

Back to Blog

Related Articles

Price Increases on Mature Renesas Electronics Products

The following price increase notice from Chris Allexandre , Senior Vice-President Sales, Marketing...

Diodes Incorporated Price Increase Notice

Notice from Diodes Incorporated 12/24/2020

Renesas fire to exacerbate tight supply

While Renesas aims to get the fab back in operation within one month, TrendForce expects the...